TaskMapper Project Management

Last updated October 9, 2024

Introducing Project Management Tools

This article covers our latest enhancements to our project management tool, designed to streamline schedule creation, resource tracking, and team collaboration. The updates focus on reducing tool clutter and providing a comprehensive solution for construction management.

Our goal is to eliminate the need for multiple tools, simplify data management, and provide real-time collaboration features that keep your entire team aligned throughout the project lifecycle.

Enhanced Schedule Creation Options

TaskMapper Project Management

Create from Scratch

Create a new schedule using intuitive tools to add tasks, milestones, and dependencies. Set custom durations, deadlines, and working hours.

Import Existing Schedule

Seamlessly import schedules from other tools while preserving hierarchical structure. Avoid data loss during transfers.

💡

Supported formats: Primavera P6 (.xer, .xml), Microsoft Projects (.mpp)

Resource & Cost Tracking

TaskMapper Project Management

New ability to track resources and costs within imported schedules, providing comprehensive project oversight.

The system now allows for complete schedule modification at any point, giving project managers greater flexibility to adapt to changing conditions without switching between multiple tools.

Real-Time Collaboration Features

Task-Specific Comments

TaskMapper Project Management

Tag team members in comments tied directly to specific activities, eliminating the need for separate communication tools.

Notification System

Receive alerts for unread comments and mentions, ensuring you never miss critical updates.

Attachment Management

TaskMapper Project Management

Easily attach and access documents related to specific tasks, with filtering options by user or time.

Schedule Sharing

TaskMapper Project Management

Share schedules with specific users and assign custom permission levels that override account settings.

Advanced Schedule Editing Capabilities

Table View Interface

TaskMapper Project Management

An Excel-like interface for quick data entry, featuring copy-paste functionality for efficient schedule building.

Task Dependencies

TaskMapper Project Management

Establish relationships between tasks with multiple dependency types (Finish-to-Start, Start-to-Start, etc.) and lag settings.

Drag-and-Drop Functionality

Easily reorganize tasks and WBS structures with intuitive drag-and-drop controls.

Critical Path Indicators

Visual highlighting of critical activities helps maintain focus on schedule-driving tasks.

Custom Weights and Progress Tracking

Define Custom Weights

Assign percentage weights to activities based on their importance to overall project completion.

Validation Indicators

System alerts when weights don't total 100%, ensuring accurate progress calculation.

Track Actual Progress

Record completion percentages against weighted activities for precise project status.

Generate Reports

Visualize progress with automatically generated charts and reports based on weighted completion.

Custom weights provide a more nuanced view of project progress, allowing managers to prioritize critical activities and get a more accurate picture of overall completion status.

Resource Management System

Add Resources

Create user resources or custom equipment resources with associated costs

Assign to Activities

Connect resources to specific tasks with planned utilization

Track Time & Usage

Record actual hours worked and units used during execution

Analyze Performance

Compare planned vs. actual resource utilization and costs

💡

The system supports both hourly-based and fixed-cost resource management, accommodating different business models across regions.

Permission Management

Account-Level Permissions

Set baseline access for users across all schedules

Schedule-Specific Permissions

Override defaults with custom access levels for individual schedules

Dependency Types and Scheduling Logic

Finish-to-Start (FS)Target task can't start until source task is complete (most common)
Start-to-Start (SS)Tasks can begin simultaneously or with specified lag
Finish-to-Finish (FF)Target task can't finish until source task is complete
Start-to-Finish (SF)Target task can't finish until source task starts
Lag SettingsAdd time buffers between dependent tasks (e.g., FS+1d)